Road & Sidewalk Construction Projects
Road & Sidewalk Projects
Roads & Sidewalks to be Improved |
Description |
Estimated Start* |
---|---|---|
Winthrop Ave. |
Final paving will be completed on Winthrop Ave in Beachmont. |
November 21-22, 2024 |
Oxford St. neighborhood |
Final paving will begin in the Oxford St. neighborhood. |
November 20, 2024 |
Winthrop Ave. |
Work will continue on Winthrop Ave in Beachmont with castings being repaired and replaced. |
November 18-19, 2024 |
Oxford St. neighborhood | Crews will be raising castings | November 15, 2024 |
670 Washington Ave. - 810 Washington Ave. | J Marchese & Sons will be repairing sidewalks and the roadway in the area. | September 1, 2024 - October 31, 2024 |
Campbell Ave. & North Shore Rd. Public Stairs | The public stairs linking Campbell Ave. and North Shore Road will be closed for reconstruction. | May 6, 2024 |
*estimated dates are subject to change due to weather and paving company's availability. Paving to follow approximately 2-4 weeks after the roadway is milled.
Water/Sewer Projects
Area Impacted | Project Explanation | Timeline |
---|---|---|
Fenno St. Penn St. Olive St. Revere Beach Parkway/Rte. 16 |
The City of Revere is set to begin the Fenno Street Drainage Improvements project in October 2024, aimed at addressing flooding issues in the Fenno and Olive Street areas due to undersized stormwater systems. The project includes the installation of 750 feet of new stormwater pipes, 11 new drain manholes, and 3 catch basins. It will enhance water quality by removing up to 25% of Total Suspended Solids and significantly reduce flooding, improving stormwater conveyance. |
October 2024 - June 2025 |
Billows Ave. Broadsound Ave. |
Sean Farrell Excavation will be working on water infrastructure in the area starting October 7th, from 8:00 A.M. to 5:00 P.M. This project is expected to take approximately one month to complete. Please note that some residents may experience temporary interruptions to their water service during this time. Those affected have already been informed about the specifics of the service interruption. We anticipate that water services will be restored promptly upon completion of the work, and there is a possibility that water may be turned back on earlier than expected. While some residents receiving this notification may not be directly impacted, we wanted to ensure everyone is informed about the ongoing work in the area. |
October 7, 2024 - November 8, 2024 |
City Wide |
10A Storm water extensions The program aims to eliminate sump pumps from the sewer system and upgrade the storm water system. |
|
Liberty Avenue Neighborhood Drainage Improvements Project |
New England Civil Engineering Corp. will begin construction on the Liberty Avenue Neighborhood Drainage Improvements Project in October 2024. This initiative, identified by the Engineering Department and Department of Public Works, aims to enhance the stormwater infrastructure to address flooding issues during rain events caused by existing undersized systems. The project will include the installation of approximately 1,450 linear feet of 12”-15” HDPE drain pipe, 17 drain manholes, and 14 catch basins. These upgrades are designed to improve stormwater quality by removing up to 25% of Total Suspended Solids (TSS) and reducing sediment and floatables in the downstream collection system. Additionally, the new infrastructure will significantly decrease flooding events and increase drainage capacity in the area. |
|
City Wide Hydrant and Valve Replacement Program |
Replacement of various aging hydrants and gate valves located throughout the city. |
|
|
Watermain Replacement Project to update aging infrastructure on North Shore Rd for better water quality and more reliable distribution system. This project has be split into two phases: Phase one will be completed first and will include North Shore Rd. from Revere St. to Shawmut St. Phase two will continue in the Spring of 2025 and continue on North Shore Rd. from Shawmut St. down to 151 VFW Parkway (Wonderland Shopping Center) North Shore Rd. entrance |
|
Traffic Alerts
Area Impacted |
Project Explanation |
Timeline |
---|---|---|
Broadway and Park Avenue intersection Broadway and Central Avenue intersection |
The MBTA is set to enhance traffic and bus flow at the Broadway and Park Avenue intersection, as well as the Broadway and Central Avenue intersection. This project involves the installation of new signal heads and cameras to optimize traffic management. Key Dates:
These improvements aim to streamline traffic flow and enhance safety for both vehicles and pedestrians. |
November 4, 2024 (Monday, 8 PM - 7 AM): November 5, 2024 (Tuesday, 8 PM - 7 AM) (If needed) November 20, 2024 (Wednesday, 3 AM) |
Fernwood Ave. Allston St.
|
National Grid and RJ Devereaux will be performing infrastructure upgrades in the area of 84 to 125 Fernwood Ave.; 14 to 60 Allston St. As part of this project, National Grid will also replace the natural gas service piping that connects the main to the customer’s gas meters. Construction hours and days: 7:00 a.m. – 4:00 p.m. Monday through Saturday. If you have any questions about this project please contact National Grid @781-663-3120 |
September 3, 2024 - November 26, 2024 |